Choosing the right generator size is the single most important decision in your purchase. Get it wrong, and you face either frequent overloads (and shutdowns) or wasted capital on capacity you will never use. This guide gives you the exact calculation method engineers use—not guesswork.
Etapa 1: Identify Your Critical Loads
List every device or system that must run during a power outage. These are your critical loads. For a typical commercial facility, that includes lighting, AVAC, segurança, Equipamento de TI, and process machinery.
Read the nameplate rating (in watts or amps) for each device. If only amps are available: Watts = Volts × Ampères. For three-phase equipment: Watts = Volts × Amps × 1.732 × Power Factor.
| Device | Watts em execução | Watts iniciais | Notas |
|---|---|---|---|
| Iluminação LED (50 fixtures) | 500 | 500 | No surge |
| HVAC System (10-tonelada) | 12,000 | 36,000 | 6x surge for compressor |
| Server Rack | 3,000 | 3,000 | UPS handles ride-through |
| Security System | 500 | 500 | Always-on |
| Elevator (20 HP) | 15,000 | 75,000 | High starting current |
Etapa 2: Calculate Running vs. Starting Power
You need two numbers:
- Executando kW: Sum of all loads’ executando watts, dividido por 1000.
- Iniciando kVA: The largest motor’s starting kVA (typically 4-6x its running kVA) plus the sum of all others’ running kVA.
The generator must satisfy both numbers. Exemplo: 30kW running total + 40kW starting surge = 50kW (62.5kVA) minimum generator.
Etapa 3: Apply Safety Margins
Never size exactly to your load. Industry best practice adds:
- 25% future expansion margin — you will add equipment later
- 10% altitude derating if above 1000m / 3280pés
- 10% temperature derating for ambient above 40°C / 104°F
Final formula: Tamanho do gerador (kVA) = (Total Running kW × 1.25) ÷ 0.8
For a detailed walkthrough with downloadable calculator, see our Guia de dimensionamento de gerador.
Common Sizing Mistakes
- Ignorando a corrente de partida do motor — motors draw 4-6x running current at startup
- Using nameplate kVA instead of kW — critical for engine loading calculations
- Forgetting power factor differences — UPS systems have harmonic loads that affect Dimensionamento do Gerador
- Adding 100% redundancy unnecessarily — N+1 for critical, standalone for non-critical
Perguntas frequentes">Perguntas frequentes
How do I size a generator for motor loads?
Multiply the largest motor’s running kVA by 4-6 (depending on starting method) and add the sum of all other loads. For soft-start motors, use 2-3x. For VFD-driven motors, use 1.5x.
Qual é o 80% rule for generator sizing?
Geradores should operate at 70-80% of rated capacity for optimal fuel efficiency. Sizing to 100% continuous load is not recommended for diesel engines as it accelerates carbon buildup.
Can I use a generator sizing calculator online?
Sim. Many manufacturers provide free sizing tools. No entanto, always validate the results with a licensed electrical engineer for critical applications.
Related Resources
- Diesel Generator Fuel Consumption Guide
- Diesel Generator Price Guide
- Guia de dimensionamento de gerador
- kW vs kVA: What’s the Difference
- 1000Gerador kVA
- 100kVA Generator Specs
⚡ Explore soluções relacionadas
- 🏭 500kW Gerador Diesel
- 🏭 1000kW Gerador Diesel
- 🏭 500Gerador diesel de kW YC
- 🔧 KMS (Cummins/Doosan) Série
- 📋 Grupos Geradores Diesel
- 📋 Processo de pedido – Como comprar
- 📋 Contate-nos
💡 Precisa de uma solução customizada? Contate nossa equipe de engenharia para recomendações específicas do projeto.