Data centers demand the highest reliability from their Notstromsysteme. A single power outage can cost millions in lost revenue, SLA penalties, and reputational damage. This guide from Huaquan Power covers everything you need to know about choosing the right generator for your data center — from sizing calculations and redundancy architectures to compliance requirements.
Schritt 1: Calculate Your Total Load
Accurate load calculation is the foundation of generator sizing. Data center loads have unique characteristics:
- IT Load: Server, Lagerung, networking — the core computing power draw
- Cooling Load: CRAC/CRAH units, chiller plants — typically 30-40% of IT load
- Facilities Load: Beleuchtung, Sicherheit, fire suppression — 5-10% of total
- UPS Charging: Recharging batteries after an outage — 10-15% of UPS rating
- Motor Starting: Chiller compressors have high inrush current — critical sizing factor
Sizing Formula
Total Generator kW = (IT Load + Cooling Load + Facilities + UPS Charging) X 1.2 Safety Factor
| Data Center Size | IT Load (kW) | Kühlung (kW) | Other (kW) | Recommended Generator (kW) |
|---|---|---|---|---|
| Klein (Edge) | 100 | 40 | 15 | 200 |
| Medium | 500 | 200 | 60 | 1,000 |
| Groß | 2,000 | 800 | 250 | 4,000 |
| Hyperscale | 10,000 | 4,000 | 1,200 | 20,000 |
Schritt 2: Design Your Redundancy Architecture
Data center redundancy is expressed as N+x, where N is the minimum required capacity:
| Redundanz | Beschreibung | Uptime Tier | Typische Anwendung |
|---|---|---|---|
| N | No redundancy — single point of failure | Tier I | Non-critical |
| N+1 | One extra unit — most common | Tier II/III | Enterprise |
| 2N | Complete mirror — no shared components | Tier III/IV | Financial/Healthcare |
| 2(N+1) | Dual system with redundancy each side | Tier IV | Mission critical |
Schritt 3: Compliance Requirements
NFPA 110 (Nordamerika)
- Ebene 1: Life safety — must start and accept load within 10 Sekunden
- Ebene 2: Non-life-safety backup — 60-second start acceptable
- On-site fuel for minimum 8 Std. (Ebene 1) oder 2 Std. (Ebene 2)
IN 16798 / ISO 8528 (Europe/International)
- Notstrom: Class EPS — start within 15 Sekunden
- Stehen zu: Class LP — start within 60 Sekunden
Schritt 4: Select Generator Configuration
For data centers, Huaquan Power recommends:
- Parallelbetrieb: Multiple Generatoren synchronized for N+1 redundancy
- Skid-Mounted or Containerized: For rooftop or ground-level installation
- SCR/Emission Control: Meeting local emission regulations
- Fernüberwachung: IoT-enabled for 24/7 visibility
- Automatischer Transferschalter (ATS): Seamless utility-to-generator transition
Huaquan Power Data Center Solutions
Huaquan Power provides turnkey generator solutions for data centers from 200kW to 20,000kW, einschließlich:
- KMS series high-performance diesel generators (500-1000kW per unit)
- Custom containerized power modules for rapid deployment
- Parallel switchgear and synchronization systems
- Remote monitoring via Huaquan Cloud platform
- Global installation and commissioning support
Explore Huaquan data center generators oder request a custom sizing analysis.